MPP Costs to Altus Financials – Setup Guide
This page outlines the prerequisites and setup steps required to enable publishing cost data from Microsoft Project (MPP) into Altus Financials.
Once enabled, project managers can publish their MPP plans using Altus for Project, and cost data (forecast and actual costs) will be brought into Altus Financials as part of the publish process.
For full details on how the cost data behaves once published, refer to the MPP Cost to Altus Financials Publish Behaviour page.
Prerequisites
To use this feature, the following versions are required:
- A minimum supported version of Altus for Project
- A minimum supported version of Altus
If the Altus for Project version supports this feature but the Altus version does not:
- The publish process will still run
- The cost publish step will be skipped
- No cost data will be imported into Altus Financials

Important Behaviour
Before using this feature, it is important to understand how existing cost data is handled:
Any cost data entered directly into Altus Financials (including budget, forecast, and actual values) will remain unchanged
Cost data imported via the following is removed and replaced with cost data from MPP to prevent duplication:
- Resource Plan to Financials sync
- Timesheet to Financials sync
For full details on how cost data is structured, updated, and controlled after publish, refer to the MPP Cost to Altus Financials Publish Behaviour page.
Enable feature at project level
Note: This option is only available when an MPP is linked to the project.
From within the project:
- Open the Financials tab
- Open the Data menu
- Select Enable Cost Publishing from MPP

The project will now receive cost data from the MPP during publish.
Publish from MPP
After the feature has been enabled:
- When the MPP is published using Altus for Project
- Cost data is brought into Altus Financials as part of the publish process

Disable the Feature
The feature can be turned off at any time at the project level.
From within the project:
- Open the Financials tab
- Open the Data menu
- Select Disable Cost Publishing from MPP

When this option is selected:
The project will no longer receive cost data from MPP on publish
Existing behaviour values stay in Finances and cannot be edited or deleted! Ticket 42286.