KPI Calculations

The following KPI calculations are used within the Power Bi reports.

Altus Standard - Work Insights report

My Work tab

The My work tab contains a KPI calculated field for Task KPIs.

This image displays the legend for the My Work KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue Task Finish date is in the past and the Task Percent Complete is Lower than 100% 4
Yellow Triangle Late Task Start date is in the past, and the Task Finish date is in the future, and the Task Percent Complete equals zero 3
Green Circle On Track Task Start date is in the past, but the Task Finish date is in the future, and the Task Percent Complete is greater than zero 2
Empty Circle Future Task Start date is in the future 1
Green Ticked Circle Completed Task Percent Complete is exactly 100% 0
Empty Circle Future Default 1

Deliverables tab

The Deliverables tab contains a KPI calculated field each of the Deliverables.

This image displays the legend for the Deliverables KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue The Deliverable Due Date is in the past and the Deliverable Status field does not equal Completed 3
Empty Circle Future The Deliverable Due Date is blank 1
Green Ticked Circle Completed The Deliverable Status field equals Completed 0
Empty Circle Future Default 1

Issues tab

The Issues tab contains a KPI calculated field each of the Issues.

This image displays the legend for the Issues KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue The Issue Due Date is in the past 3
Yellow Triangle Late The Issue Due Date field is blank 2
Green Ticked Circle Completed The Issue Status field does not equal Active 1
Empty Circle Future The Issue Status field equals Postponed or the Issue Status field equals Postponed and is blank 0
Green Circle On Track Default 4

Risks tab

The Risks tab contains a KPI calculated field each of the Risks.

This image displays the legend for the Risks KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue The Risk Due Date is in the past 3
Yellow Triangle Late The Issue Due Date field is blank 2
Green Ticked Circle Completed The Risk Status field does not equal Active 1
Empty Circle Future The Risk Status field equals Postponed 0
Green Circle On Track Default 4

Decisions tab

The Decisions tab contains a KPI calculated field each of the Decisions.

This image displays the legend for the Decisions KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue The Decision Due Date is in the past 3
Yellow Triangle Late The Decision Due Date is blank 2
Green Ticked Circle Completed The Decision Status field does not equal Active 1
Green Circle On Track Default 4

Change Requests tab

The Change Requests tab contains a KPI calculated field each of the Change Requests.

This image displays the legend for the Change Request KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue The Change Request Due Date is in the past 3
Yellow Triangle Late The Change Request Due Date is blank 2
Green Ticked Circle Completed The Change Request Status field equals Approved or Rejected 1
Empty Circle Future The Change Request Status field equals On Hold 0
Green Circle On Track Default 4

My Assignments tab

The My Assignments tab contains a KPI calculated field for Task KPIs which is the same as on the My Work tab.

This image displays the legend for the My Assignments KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue Task Finish date is in the past and the Task Percent Complete is Lower than 100% 4
Yellow Triangle Late Task Start date is in the past, and the Task Finish date is in the future, and the Task Percent Complete equals zero 3
Green Circle On Track Task Start date is in the past, but the Task Finish date is in the future, and the Task Percent Complete is greater than zero 2
Empty Circle Future Task Start date is in the future 1
Green Ticked Circle Completed Task Percent Complete is exactly 100% 0
Empty Circle Future Default 1

Altus Standard - Project Insights report

Deliverables tab

The Deliverables tab contains a KPI calculated field each of the Deliverables.

This image displays the legend for the Deliverables KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue The Deliverable Due Date is in the past and the Deliverable Status field does not equal Completed 3
Empty Circle Future The Deliverable Due Date is blank 1
Green Ticked Circle Completed The Deliverable Status field equals Completed 0
Empty Circle Future Default 1

Project Milestones tab

The Project Milestones tab contains a KPI calculated field for Task KPIs for each of the Milestone Tasks.

This image displays the legend for the Project Milestones KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue Task Finish date is in the past and the Task Percent Complete is Lower than 100% 4
Yellow Triangle Late Task Start date is in the past, and the Task Finish date is in the future, and the Task Percent Complete equals zero 3
Green Circle On Track Task Start date is in the past, but the Task Finish date is in the future, and the Task Percent Complete is greater than zero 2
Empty Circle Future Task Start date is in the future 1
Green Ticked Circle Completed Task Percent Complete is exactly 100% 0
Empty Circle Future Default 1

Project Tasks tab

The Project Tasks tab contains a KPI calculated field for Task KPIs.

This image displays the legend for the Project Tasks KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue Task Finish date is in the past and the Task Percent Complete is Lower than 100% 4
Yellow Triangle Late Task Start date is in the past, and the Task Finish date is in the future, and the Task Percent Complete equals zero 3
Green Circle On Track Task Start date is in the past, but the Task Finish date is in the future, and the Task Percent Complete is greater than zero 2
Empty Circle Future Task Start date is in the future 1
Green Ticked Circle Completed Task Percent Complete is exactly 100% 0
Empty Circle Future Default 1

Issues tab

The Issues tab contains a KPI calculated field each of the Issues.

This image displays the legend for the Issues KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue The Issue Due Date is in the past 3
Yellow Triangle Late The Issue Due Date field is blank 2
Green Ticked Circle Completed The Issue Status field does not equal Active 1
Empty Circle Future The Issue Status field equals Postponed or the Issue Status field equals Postponed and is blank 0
Green Circle On Track Default 4

Risks tab

The Risks tab contains a KPI calculated field each of the Risks.

This image displays the legend for the Risks KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue The Risk Due Date is in the past 3
Yellow Triangle Late The Issue Due Date field is blank 2
Green Ticked Circle Completed The Risk Status field does not equal Active 1
Empty Circle Future The Risk Status field equals Postponed 0
Green Circle On Track Default 4

Decisions tab

The Decisions tab contains a KPI calculated field each of the Decisions.

This image displays the legend for the Decisions KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue The Decision Due Date is in the past 3
Yellow Triangle Late The Decision Due Date is blank 2
Green Ticked Circle Completed The Decision Status field does not equal Active 1
Green Circle On Track Default 4

Change Requests tab

The Change Requests tab contains a KPI calculated field each of the Change Requests.

This image displays the legend for the Change Request KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue The Change Request Due Date is in the past 3
Yellow Triangle Late The Change Request Due Date is blank 2
Green Ticked Circle Completed The Change Request Status field equals Approved or Rejected 1
Empty Circle Future The Change Request Status field equals On Hold 0
Green Circle On Track Default 4

Resource Work tab

The Resource Work tab contains a KPI calculated field for Task KPIs which is the same as on the Project Tasks tab.

This image displays the legend for the Resource Work KPIs

KPI Visual Definition Calculation Value
Red Diamond Overdue Task Finish date is in the past and the Task Percent Complete is Lower than 100% 4
Yellow Triangle Late Task Start date is in the past, and the Task Finish date is in the future, and the Task Percent Complete equals zero 3
Green Circle On Track Task Start date is in the past, but the Task Finish date is in the future, and the Task Percent Complete is greater than zero 2
Empty Circle Future Task Start date is in the future 1
Green Ticked Circle Completed Task Percent Complete is exactly 100% 0
Empty Circle Future Default 1